If you haven’t been to church latel, here’s a photo of progress on our project.

Please note the following:

  • The scaffolding on the south-east corner has been dismantled
  • Copper eavestroughs for this portion of the roof has been installed although downspouts still need to be added.
    These will be installed using a skyjack lift later.
  • Lead coated copper flashings for this section of the roof have been installed.
  • Copper work for the weathervane/lightning arrestor has been installed and copper flashings installed for the section of the spire above the green safety meshing.
  • Mortar repairs are at about the 50 foot level and moving downwards.  Propane heaters are being used to prevent the grout from freezing.