If you haven’t been to church latel, here’s a photo of progress on our project.

Please note the following:

  • The scaffolding on the south-east corner has been dismantled
  • Copper eavestroughs for this portion of the roof has been installed although downspouts still need to be added.
    These will be installed using a skyjack lift later.
  • Lead coated copper flashings for this section of the roof have been installed.
  • Copper work for the weathervane/lightning arrestor has been installed and copper flashings installed for the section of the spire above the green safety meshing.
  • Mortar repairs are at about the 50 foot level and moving downwards.  Propane heaters are being used to prevent the grout from freezing.

Return to Restore the Roof

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.